Asante Gold Set to Ship Key Equipment for Bibiani Sulphide Recovery Plant

Asante Gold Set to Ship Key Equipment for Bibiani Sulphide Recovery Plant

Asante Gold Corporation has announced that the principal long-lead equipment for the Sulphide Recovery Plant at the Bibiani Gold Mine is expected to be shipped by mid-August 2024.

The new facility is crucial for Asante’s strategy to increase gold production at Bibiani to over 250,000 ounces annually, aiming for a cumulative production of 1.2 million ounces over the next five years. This plan, outlined in the 2024 Bibiani Technical Report, also projects lower all-in sustaining costs (AISC). The installation of the Sulphide Recovery Plant is anticipated to significantly enhance gold recovery from sulphide ore, increasing it from 70% to approximately 92%, which will positively impact profit margins.

The company has made significant progress on the Sulphide Recovery Plant, with 50% of the civil works completed. Fabrication of the long-lead equipment is finalized, and the items are being prepared for shipment to the Bibiani site, expected to arrive by mid-August 2024.

Upon completion of the Sulphide Recovery Plant, Asante anticipates producing around 20,000 ounces of gold per month at Bibiani, aligning with the company’s long-term production goals. Asante is committed to optimizing its operational mines and enhancing production efficiency. icon

    Subscribe to the most timely news about the metals market

    Metals Wire's weekly digest for mining and processing industry professionals, investors, analysts, journalists.