Galan Lithium Advances Construction at Hombre Muerto West for 2025 Lithium Production

December 21, 2023

Galan Lithium has announced significant progress in the construction of the Hombre Muerto West (HMW) Phase 1 lithium brine project, aligning with its target to commence lithium chloride production in the first half of 2025.

Phase 1 Construction Progressing Smoothly

Key developments in the project include:

- Pond 1 construction nearing completion, currently at an 85% completion rate.

- Operational on-site laboratory for continuous lithium assaying.

- The lining crew set to begin work on Pond 1, with installation starting before the year's end.

- Filling of Pond 1 is anticipated to begin in Q1 2024, with the evaporation process expected to start in the upcoming summer.

- Initiation of Pond 2 construction is projected before the end of this year.

Phased Approach to Lithium Production

Galan Lithium has outlined a multi-phase strategy for the HMW project:

- The initial Phase 1 targets the production of 5.4ktpa LCE (lithium carbonate equivalent) of lithium chloride concentrate by H1 2025.

- Phase 2 aims to increase production to 21ktpa LCE in 2026.

- Subsequent phases include increasing production to 40ktpa LCE by 2028 (Phase 3) and 60ktpa LCE by 2030 (Phase 4).

- Phase 4 also plans to incorporate lithium brine from Galan’s Candelas project, another 100% owned venture in Argentina.

    Subscribe to the most timely news about the metals market

    Metals Wire's weekly digest for mining and processing industry professionals, investors, analysts, journalists.
    By signing up you agree to the Metals Wire
    Privacy Statement