Galan Lithium Initiates Maiden Filling of Pond 1 at Hombre Muerto West

January 23, 2024

Galan Lithium has announced the commencement of the initial filling of Pond 1 at its Hombre Muerto West (HMW) Phase 1 lithium brine project. This marks a step in the project's progress towards lithium chloride production, expected in the first half of 2025.

Project Developments and Expectations

- The initial filling of Pond 1 has begun, with the evaporation process set to start within two weeks following the completion of quality testing. This step is integral to the long-term production schedule of the HMW Project.

- The liner installation for Pond 1 is rapidly advancing, currently at 40% completion, while the construction of Pond 2's earthworks is also progressing well, with 20% completion.

- The HMW Project aims to produce a premium high-grade lithium chloride concentrate with a 6% Li content, equivalent to 13% Li2O or 32% Lithium Carbonate Equivalent (LCE), by the first half of 2025.

- Galan Lithium boasts low all-in sustaining costs, positioning HMW in the first quartile of the lithium industry’s cost curve, with an operating cost of $US3,510/t LCE.

Future Prospects and Ongoing Activities

- An updated resource estimate for the project is anticipated in the first quarter of 2024.

- Additionally, Galan Lithium is preparing for a due diligence site visit by Glencore later this week.

    Subscribe to the most timely news about the metals market

    Metals Wire's weekly digest for mining and processing industry professionals, investors, analysts, journalists.
    By signing up you agree to the Metals Wire
    Privacy Statement